Initial Velocity

There are occasions when one needs to predict team velocity when there is no historical data available. Here is a good example of how we can establish an initial velocity. This has been adapted from Crisps Blog pages.

“This is how you can get started. Take a well known task/story as your standardised benchmark. If this a rather small story, set it to two story points so you have room for smaller stories. Estimate the rest of the stories relative to this.

Before our first planning meeting we need to know our velocity so we know how much we can commit to. But we don’t have that since we don’t have a history.

To get an initial velocity for our first sprint, we estimate the selected standard story in ideal man days. Let’s say the story is 2 story points and 4 ideal man days, we then know the team can handle 1/2 story point per ideal man day. Use the focus factor to convert ideal man day to calendar days. The focus factor is typically between 50% and 70% depending on the amount of support and interruptions. If the focus factor is 50% we can handle 1/4 story point in a calendar day (1/2 * 50%). If the team consist of five people and the sprint is 14 days we have 70 calendar man days in the sprint. 70 * 1/4 gives that we should be able to bring 17 story points into the sprint. Finally we have our initial velocity.”

Hope you liked it.

Cheers!!! Happy Scrumming.

Advertisements
  1. No comments yet.
  1. No trackbacks yet.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: